top of page

Northwest Region Construction Update - June 19th

  • 11 minutes ago
  • 20 min read

The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.




Ashland County


Highway: Prentice Avenue

Location: US 2 (Lake Shore Drive) to 6th Street East in Ashland

Schedule: May 4 to early July

Cost: $845,876

Description of work: Replacing the existing pavement structure, making subgrade improvements, modifying the vertical profile of the road to allow for better tie-ins, replacing substandard curb ramps, curb and gutter, adding two inlets just south of 3rd Street and replacing pavement markings and signage

Traffic impacts: Prentice Avenue is closed.


Highway: County GG

Location: McCarthy Creek Bridge southwest of Mellen

Schedule: May 26 to late July

Cost: $665,275

Description of work: Replacing the bridge, reconstructing the pavement on both sides of the bridge and replacing guardrail

Traffic impacts: County GG is closed from Conley Road to Clam Lake Road

  • Traffic is being detoured via WIS 13 and WIS 77.



Ashland and Sawyer counties


Highway: WIS 13 and WIS 77

Location: WIS 13, Price County line to Morse Road between Mellen and Glidden, and WIS 77, Teal River Bridge northeast of Hayward

Schedule: WIS 13, April 27 to late October; Work on WIS 77 expected to start in August

Cost: $5.19 million

Description of work: WIS 13, replacing, resetting, extending or abandoning more than 50 existing culvert pipes and constructing a new box culvert at Becky Creek; making concrete surface repairs at the bridge over Dryden Creek northwest of Glidden; patching the deck on the bridge over the Chippewa River southeast of Glidden; overlaying the deck with concrete on the bridge over Butternut Creek south of Butternut; and replacing guardrail at the structures and one other location in the project limits; WIS 77, milling and overlaying the existing bridge deck, overlaying concrete pavement approach slabs, milling and overlaying roadway approaches, making concrete surface repairs on parapets, grouting voids under abutments, supplementing riprap at abutments, adjusting guardrail and installing new pavement markings

Traffic impacts: WIS 13 remains open to traffic, but motorists will encounter:

  • Single-lane closures controlled by temporary traffic signals at the Butternut Creek, East Fork Chippewa River and Becky Creek and active culvert pipe installations

    • Signals at Butternut Creek, East Fork Chippewa River and Becky Creek are in place continuously. Those at culvert pipe locations are in place during work hours only.

  • Single-lane closures controlled by flagging during paving at culvert sites



Barron County


Highway: County O

Location: East Branch Upper Pine Creek Bridge north of the village of Dallas

Schedule: June 15 to early August

Cost: $ $501,425

Description of work: Replacing the bridge and reconstructing 149.5 feet of approaching roadway

Traffic impacts: County O is closed at the structure, and traffic is being detoured via County D, WIS 25 and County U.


Highway: County O

Location: Wisconsin Avenue intersection in Rice Lake

Schedule: April 20 to late September

Cost: $1.1 million

Description of work: Realigning and extending the County O left-turn lanes, constructing right-turn lanes both north and south along Wisconsin Avenue, replacing traffic signals and adding sidewalk and a pedestrian crossing on County O

Traffic impacts: Wisconsin Avenue and County O remain open to traffic, but motorists will encounter lane closures for the installation of new traffic signals.


Highway: US 53 South

Location: Bridges between Cameron and New Auburn, structures over US 8, Knapp Street, County A, County AA and Carlson School Road, 2025; and structures over 20th Street, County I and the Chetek River, 2026

Schedule: Feb. 23 to October, 2026 construction; May 5, 2025, to October 2026, overall project

Cost: $10.91 million

Description of 2026 work: Replacing the decks on the bridges over the Chetek River and 20th Street; replacing the bridge over County I; milling pavement on both sides of each structure and placing new asphalt pavement on the approaches; milling and overlaying the pavement on the southbound US 53 on- and off-ramps at the County I interchange; and replacing guardrail, pavement markings and signage

Traffic impacts: Southbound US 53 remains open to traffic, but motorists will encounter:

  • Continuous single-lane closures on southbound US 53 from north of US 8 to south of 20th Street southwest of Cameron, north of Knapp Street in Chetek to south of County AA southeast of Chetek and from north of Carlson School Road, located northwest of New Auburn, to south of the structure

    • The speed limit is reduced to 55 mph.

  • Single-lane closures on County I through the duration of the project

  • Closure of the ramp from County I to southbound US 53

    • The ramp closure is anticipated to be in place through Oct. 1.

    • Traffic is being detoured on northbound US 53 to the US 8 interchange, where motorists will exit and then re-enter southbound US 53.


Highway: US 63

Location: Charrie Lane in Cumberland to the Washburn County line

Schedule: April 13 to late June

Cost: $4.64 million

Description of work: Removing a portion of the existing pavement and paving new asphalt, installing centerline and edge line rumble strips, cleaning or repairing culverts, reconstructing sidewalk curb ramps to Americans With Disabilities Act (ADA) compliance and placing new pavement markings

Traffic impacts: US 63 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging from:

  • 6 a.m. to 9 p.m. Mondays through Thursdays

  • 6 a.m. to 2 p.m. Fridays


Highway: US 63

Location: Beaver Dam Lake in Cumberland

Schedule: April 24 to early September

Cost: $2.64 million

Description of work: Removing the existing box culvert carrying Beaver Dam Lake under US 63, building a bridge with a longer span to replace the box culvert, removing the Lake Street Bridge, dredging Beaver Dam Lake under US 63 and the Lake Street Bridge, building an ATV trail on the east side of US 63 from Arcade Avenue to Nedvidek Street, reconstructing US 63 on both sides of the new bridge, reconstructing portions of Lake Street, Nedvidek Street and Babcock Avenue to match the raised profile of US 63 and constructing curb, gutter and sidewalk

Traffic impacts: US 63 is closed to traffic on both sides of the structure.

  • Traffic is being detoured via WIS 48, US 53 and WIS 70. In addition:

  • Lake Street is closed just past the boat landing.

§  Access to the boat landing is being maintained.

§  The Lake Street Bridge is open to emergency vehicles only through late July.



Bayfield County


Highway: WIS 13

Location: Little Whittlesey Creek

Schedule: June 8 to mid-October

Cost: $1.5 million

Description of work: Constructing a temporary bypass to carry WIS 13 traffic during construction, replacing the culvert pipes with a bridge, milling and paving about 1,000 feet of pavement approaching the bridge, restoring the stream bed, installing new guardrail, relocating the driveway of the US Fish and Wildlife Service facility, adding riprap and removing the temporary bypass

Traffic impacts: WIS 13 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging.

  • Traffic is expected to be switched to the temporary bypass the week of June 22.


Highway: US 2

Location: North Fish Creek Bridge southwest of the intersection of US 2 and WIS 13

Schedule: April 13 to mid-July

Cost: $1.69 million

Description of work: Replacing the bridge deck, repairing an abutment, resetting an inlet, completing minor paving on both sides of the bridge to adjust and smooth out roadway approaches and adjusting guardrail

Traffic impacts: US 2 is reduced to a single lane at the bridge.

  • The open lane has a maximum width of 13 feet.

  • Temporary traffic signals are controlling use of the single lane.

  • The alternative oversize-overweight truck route follows US 53, WIS 77, WIS 13 and WIS 112.



Buffalo County


Highway: County P

Location: Trempealeau River Bridge east of Fountain City in the town of Buffalo

Schedule: Feb. 23 to mid-October

Cost: $1.78 million

Description of work: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing temporary bypass and structure

Traffic impacts: County P remains open to traffic, but motorists are using a temporary road and bridge to bypass the work zone.

  • They might encounter flagging at the site for hauling in equipment and materials.

  • In addition, buoys have been added upstream and downstream to alert boating traffic of construction.


Highway: WIS 35 and WIS 54

Location: WIS 35, Indian Creek Road to old WIS 35; and WIS 54, Minnesota state line to WIS 35

Schedule: April 23 to early July

Cost: $6.41 million

Description of work: WIS 35, milling and overlaying the asphaltic pavement; repairing or replacing culverts to address deterioration; adjusting, repairing or replacing guardrail; improving drainage along WIS 35 just west of Lovers Lane; upgrading curb ramps to meet Americans With Disabilities Act standards; installing centerline and shoulder rumble strips; and adding new pavement markings; WIS 54, milling and overlaying the asphaltic pavement, replacing weigh-in-motion sensors in the roadway; installing centerline and shoulder rumble strips; and adding new pavement markings

Traffic Impacts: WIS 35 and WIS 54 remain open to traffic, but motorists will encounter lane and shoulder closures controlled by flagging.



Burnett County


Highway: WIS 35

Location: Lanquist Street in Siren to WIS 70 East

Schedule: May 4 to mid-October

Cost: $8.55 million

Description of work: Replacing pavement with new concrete from Lanquist Street to Southshore Drive, replacing storm sewer and expanding its capacity from Lanquist to Works Progress Street, resurfacing the roadway from Southshore Drive to WIS 70 East, reviewing and revising access points, improving turning movements in all quadrants at the WIS 35 and WIS 70/County B intersection in the city of Siren, replacing traffic signals, replacing curb ramps and removing extra lanes from Park Street to Northshore Drive to reduce flooding potential

Traffic impacts: WIS 35 remains open to traffic, but motorists will encounter:

  • Shoulder closures on northbound WIS 35 from Lanquist Street to Bradley Street; southbound WIS 35 from the WIS 35/70 intersection to Bacon Street; and east- and westbound WIS 70 from 1st Avenue to the WIS 35/70 intersection

  • Lanes closures controlled by flagging on north- and southbound WIS 35 from Southshore Drive to the roundabout

  • Various single-lane closures controlled by flagging on north- and southbound US 53 from Southshore Drive to WIS 35/70 roundabout

  • Starting today, only southbound traffic is allowed on WIS 35 from Lanquist Street to Southshore Drive, and northbound car and all heavy truck traffic will be detoured.

  • Northbound car detour: County B, 4th Avenue North and Elizabeth Street.

  • Truck detour: WIS 70/MN 70, I-35 (MN), MN 48/WIS 77 and WIS 35.



Chippewa County


Highway: 205th Avenue

Location: McCann Creek Bridge northeast of Bloomer

Schedule: May 4 through early July

Cost: $522,421

Description of work: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing the temporary bypass and structure

Traffic Impacts: Traffic has been moved to the new structure, but motorists might encounter lane closures as finishing work is completed.


Highway: WIS 124

Location: Duncan Creek Bridge to County S

Schedule: April 13 to mid-June

Cost: $2.68 million

Description of work: Milling off a portion of the pavement and placing new asphalt pavement, resurfacing the County S roundabout and replacing the central island truck apron pavement, replacing culverts, cleaning ditches, upgrading sidewalk curb ramps and replacing pavement markings

Traffic Impacts: None; current operations have ceased until Monday, July 20, when work is set to begin on the WIS 124/County S roundabout.

  • During work on the roundabout - anticipated to run from July 20 through Thursday, Aug. 6, the roundabout will be closed.

    • Traffic will be detoured via Business 29 (West River Street), US 53 and County B.


Highway: US 53

Location: 40th Avenue in Lake Hallie to County B in the town of Tilden

Schedule: March 2 to late June, 2026 construction; and April 1, 2024, to late June 2026, overall project

Cost: $36.6 million

Description of 2026 work: Replacing the pavement on southbound US 53 south of County N, widening the shoulder on the ramp from Business 29/County X to southbound US 53, placing polymer overlays on the southbound US 53 bridges over the Chippewa River and BUS 29/County X, replacing guardrail, completing culvert work, building permanent maintenance crossovers, installing new pavement markings and shoulder rumble strips and removing temporary crossovers used during construction

Traffic Impacts: US 53 remains open to traffic, but:

  • All ramps at the US 53/BUS 29/County X interchange will be open by the end of the day today.

    • The ramp from County X/BUS 29 to southbound US 53 is scheduled to be closed the morning of Friday, June 26.

  • Motorists will encounter inside single-lane closures at the BUS 29/County X interchange from Monday to Thursday, June 22-25. 

  • The speed limit is reduced to 55 mph where there are lane closures.



Chippewa and Clark counties


Highway: WIS 29

Location: 320th Street east of Boyd to Koser Avenue west of Thorp

Schedule: May 11 to mid-September

Cost: $9.35 million

Description of work: Patching the concrete pavement, placing 3.75 inches of asphalt over the existing roadway, removing a portion of the existing pavement on the WIS 29 on- and off-ramps at the County H interchange in Stanley and on County H between the east- and westbound ramps and placing new asphalt pavement, repairing culverts as needed, rehabilitating the structure over Hay Creek east of Boyd and closing and removing the intersection on WIS 29 at 320th Street per the town of Delmar’s request

Traffic impacts: WIS 29 remains open to traffic, but:

  • Motorists will encounter single-lane closures in both directions the entire length of the project.

  • The ramp from eastbound WIS 29 to County H is closed through 6 a.m. Monday, June 22.

  • All traffic control will be removed from east- and westbound WIS 29 from 6 p.m. Wednesday, June 24 through 6 a.m. Monday, June 29 for the Hoofbeat Festival.



Clark County


Highway: WIS 29

Location: County D in Owen to WIS 13 in Abbotsford

Schedule: March 30 to early October

Cost: $17.37 million

Description of work: Repairing the existing concrete pavement on WIS 29 and the ramps at the County E interchange and then overlaying the roadway and ramps with asphalt pavement; overlaying the ramps at Cardinal Avenue east of Owen and Hi Line Avenue in Abbotsford with asphalt; replacing guardrail to meet current WisDOT standards; repairing the decks on the east- and westbound WIS 29 bridges over County D and the railroad tracks to the east and placing a thin bonded polymer overlay over them; cleaning and repairing culverts to improve drainage; repairing the median inlets near Owen adjacent to concrete barrier wall; and completing minor grading of ditches

Traffic Impacts: WIS 29 remains open to traffic, but motorists will encounter single-lane closures in both directions where crews are working.

  • The speed limit in that area is reduced to 55 mph.



Douglas County


Highway: County B

Location: Lake Nebagamon Creek Bridge east of US 53

Schedule: May 18 to mid-July

Cost: $565,907

Description of work: Replacing the bridge, reconstructing pavement on both sides of the bridge and grading

Traffic Impacts: County B is closed at the bridge.


Highway: WIS 13

Location: Bridge over US 2/53 southeast of Superior

Schedule: June 8 to late July

Cost: $1.43

Description of work: Replacing bridge joints, making surface repairs to abutments, cleaning and painting bridge girders and bearings, replacing concrete approach slabs at each end of bridge, replacing asphalt roadway approaches for about 100 feet and replacing the guardrail bridge connections

Traffic Impacts: WIS 13 and US 2/53 remain open to traffic, but WIS 13 is reduced to a single lane of traffic on the bridge controlled by temporary traffic signals.


Highway: WIS 105

Location: Unnamed tributary of the Pokegama River in Superior

Schedule: June 15 to late October

Cost: $3.06 million

Description of work: Removing the existing culvert, building a temporary bypass to carry a single lane of traffic during construction, constructing a bridge to replace the culvert, replacing pavement approaching the new structure, installing guardrail, removing the temporary bypass and repairing slopes disturbed by construction

Traffic Impacts: WIS 105 remains open to traffic, but the roadway is reduced to a single lane of traffic controlled by traffic signals.



Dunn County


Highway: County P

Location: Irving Creek west of Menomonie

Schedule: May 18 to early July

Cost: $547,773

Description of work: Replacing the structure with a twin-cell box culvert and reconstructing pavement on both sides of the new structure

Traffic Impacts: County P is closed at the structure.


Highway: County Q

Location: North Branch Wilson Creek Bridge northwest of Knapp

Schedule: June 8 to late July

Cost: $430,297

Description of work: Replacing the bridge and reconstructing pavement on both sides of the new structure

Traffic Impacts: County Q is closed at the structure.


Highway: WIS 25

Location: I-94 in Menomonie to County D

Schedule: April 16 to early August

Cost: $4.98 million

Description of work: Removing a portion of the existing pavement from the bridge over I-94 to the railroad bridge and placing new asphalt pavement; recycling a portion of the existing pavement, mixing it with a stabilizing agent, relaying it and placing new asphalt over the roadway from the railroad bridge to County D; adjusting or replacing guardrail; and upgrading pedestrian curb ramps and traffic signals

Traffic Impacts: WIS 25 is open to traffic, but motorists will encounter single-lane closures between I-94 and Cedar Falls Road.

  • In addition, motorists will encounter single-lane closures on the north end of the project once paving begins.


Highway: WIS 85

Location: Just west of the north junction of County O west of Rock Falls to approximately 2,100 feet west of 1010th Street northeast of Caryville

Schedule: April 27 to mid-August

Cost: $3.94 million

Description of work: Removing a portion of the existing pavement from just west of the north junction of County O to the south junction of County H and placing new pavement, removing and recycling a portion of the existing pavement from the south junction of County H to approximately 2,100 feet west of 1010th Street and overlaying the roadway with new pavement, widening the paved shoulders from 3 to 5 feet, installing centerline and shoulder rumble strips from the south junction of County H to about 2,100 feet west of 1010th Street, replacing the existing drainage structure under WIS 85 east of the north junction of County H with a dual box culvert, replacing a cattle pass that is no longer used with a culvert pipe, removing guardrail and improving the Chippewa River State Trail crossing to meet Americans With Disabilities Act standards

Traffic Impacts: WIS 85 is closed to through traffic from County O to Fuller Road.

  • Through traffic is being detoured via WIS 37 and US 10.

  • Access is being maintained to homes and businesses in the work zone.

However:

  • WIS 85 is impassable between the north leg of County H and Fuller Road.

  • This work is expected to be completed the week of June 22.

  • Motorists will encounter lane closures controlled by flagging operations where cold-in-place recycling operations are.


Highway: US 12 and WIS 40

Location: US 12, Princeton Drive in Elk Mound to just north of WIS 29; and WIS 40, US 12 to County M in the village of Colfax

Schedule: March 30 to October

Cost: $8.99 million

Description of work: Milling 2.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in rural areas; milling 3.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in urban areas; replacing joints on the Eighteen Mile Creek Bridge in village of Colfax; placing centerline rumble strips in rural areas; replacing cross culverts, guardrail and sidewalk curb ramps; and replacing the railroad crossing in the village of Colfax

Traffic Impacts: US 12 and WIS 40 remain open to traffic, but motorists will encounter:

  • Shoulder and parking lane closures in Colfax

  • Single-lane closures controlled by an automated flagger assistance device needed from Elk Mound through Colfax



Eau Claire County


Highway: Gravel Pit Road

Location: Hay Creek Bridge north of Augusta

Schedule: May 26 to early July

Cost: $396,980

Description of work: Replacing the bridge and reconstructing roadway on both sides of the structure

Traffic Impacts: Gravel Pit Road is closed at the bridge.


Highway: WIS 93, WIS 312 and US 12

Location: WIS 93, East Hamilton Avenue, Eau Claire, to Deerfield Road, town of Washington; WIS 312, Old Wells Road to US 53, all in Eau Claire; and US 12: Truax Boulevard, Eau Claire, to Mayer Road, Altoona

Schedule: March 30 to mid-September

Cost: $2.91 million

Description of work: Reconstructing noncompliant curb ramps and upgrading pedestrian crossings that aren’t consistent or not fully provided where needed

Traffic Impacts: The following traffic impacts are anticipated for the coming week on:

  • Northbound WIS 93

    • Hamilton Avenue: Single-lane closures; fully opened by 11 a.m. daily

  • Westbound US 12

    • Hastings Way: Right-turn lane closure; fully opened when work isn’t being performed

    • University Avenue: Right-turn lane closure; fully opened when work is not being performed

    • US 53: Single-lane closure

    • US 53 to Otter Road: Single-lane closures from 8 p.m. to 6 a.m.; fully open when work isn’t being performed

  • Eastbound US 12

    • Otter Road: Right-turn lane closure; fully opened when work isn’t being performed

    • University Avenue: Right-turn lane closure; fully opened when work isn’t being performed


Highway: I-94

Location: US 53 interchange to Mallard Road southwest of Eau Claire

Schedule: March 23 to late November, 2026 construction; and March 4, 2024, to late November 2026, overall project

Cost: $69.9 million

Description of 2026 work: Replacing the pavement on eastbound I-94 from Otter Creek to Mallard Road, the eastbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under eastbound I-94 near County D; completing shoulders, removing temporary lanes and structures and restoring the interstate’s median

Traffic Impacts: Motorists will encounter lane closures in both directions during off-peak travel times and a reduced speed limit of 60 mph in the work zone.

  • County D is closed at I-94.

    • Traffic is being detoured via US 53, County J, County IJ and County JJ.



Pepin County


Highway: Dorwins Mill Road

Location: Bear Creek Bridge east of Durand

Schedule: May 18 to late July

Cost: $679,659

Description of work: Replacing the bridge and reconstructing roadway on both sides of the structure

Traffic Impacts: Dorwins Mill Road is closed at the bridge.



Pierce County


Highway: WIS 65 and US 10

Location: Culverts carrying a branch of Goose Creek and branch of the south fork of the Kinnickinnic River under WIS 65 between River Falls and Ellsworth and culverts carrying unnamed drainageways under US 10 southeast of Ellsworth

Schedule: March 23 to early August

Cost: $2.15 million

Description of work: Replacing culvert C-47-2 and C-47-5 on WIS 65, reconstructing the roadway and removing guardrail; repairing the wing walls on culvert C-47-236 on US 10 and replacing guardrail at that location; and replacing culvert C-47-242 on US 10, reconstructing the road where work is being completed, replacing the guardrail on the north side of the highway and removing guardrail on the south side

Traffic impacts: US 10 is restricted to a single lane of traffic controlled by temporary traffic signals southeast of Ellsworth.

  • Both lanes are expected to be open the afternoon of Tuesday, June 23, weather permitting.



Polk County


Highway: WIS 46

Location: US 8 to WIS 35

Schedule: April 15 to early October

Cost: $8.49 million

Description of work: Recycling 4 inches of pavement in place on the rural portion of the project; placing 2.75 inches of new asphalt and installing centerline rumble strips; milling 3.25 inches of pavement in the village of Balsam Lake and placing 3.35 inches of new asphalt; cleaning, extending, lining or replacing culverts; replacing or adjusting existing guardrail; and replacing curb ramps in the village of Balsam Lake

Traffic impacts: WIS 46 is closed from 140th Avenue to 150th Avenue.

  • This closure is anticipated to be in place through mid-July.

  • Traffic is being detoured via US 8 and WIS 35.

  • Motorists might encounter single-lane closures controlled by flagging on other segments of the project.


Highway: US 8

Location: WIS 35 North to WIS 46 South

Schedule: May 11 to late August

Cost: $7.52 million

Description of work: Milling 2.25 inches of existing asphaltic surface and placing 3.25 inches new asphalt; reconstructing two locations of roadway where sloughing is occurring; widening the paved shoulders from 3 to 5 feet; installing centerline and shoulder rumble strips; cleaning, extending, lining or replacing existing culverts and replacing deteriorating end walls on some structures; replacing or adjusting guardrail; and completing roadside maintenance, including clearing and ditching

Traffic impacts: US 8 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging for paving operations.



St. Croix County


Highway: WIS 35/64 and WIS 64

Location: WIS 35/64, 150th Avenue northeast of Houlton to County C; and WIS 64, WIS 35 to 142nd Street in New Richmond

Schedule: April 13 to September

Cost: $9.96 million

Description of work: Performing spot repairs on the driving lanes in both directions where deterioration exists, overlaying existing concrete with asphalt at select locations in both directions of travel, installing new pavement markings and shoulder rumble strips, resurfacing the existing shoulders, replacing guardrail at structures and signage and cleaning or riprapping culvert end walls

Traffic Impacts: WIS 35/64 and WIS 64 remain open to traffic, but motorists will encounter lane closures throughout the project limits.

  • Starting Monday, June 22, the ramp from southbound WIS 35/64 to County V, the ramp from County V to northbound WIS 35/64, the ramp from eastbound County C/WIS 35 to WIS 35/64 and ramp from WIS 35/64 to County C are scheduled to close through Wednesday, June 24.

  • The ramp from County VV to northbound WIS 35/64, the ramp from WIS 35/64 to County VV, the ramp from eastbound WIS 35/64 to County A and the ramp from County A to westbound WIS 35/64 are tentatively scheduled to close Thursday, June 25.

  • Detour routes are posted for ramp closures.

All ramp closure schedules are weather dependent.


Highway: WIS 128

Location: US 12 to WIS 170 in Glenwood City

Schedule: May 26 to late August

Cost: $6.08 million

Description of work: Recycling 3.75 inches of the existing asphaltic surface and paving 2.75 inches over the recycled pavement in the rural section of the project; milling approximately 3.25 inches of the existing asphaltic surface and paving the roadway with 3.25 inches of hot-mix asphalt in the urban section; placing centerline rumble strips; overlaying the deck on the bridge over Tiffany Creek in Glenwood City; updating guardrail throughout the project corridor; cleaning or replacing culvert pipes; updating sidewalk curb ramps in Glenwood City; and installing new pavement markings

Traffic Impacts: WIS 128 is closed to through traffic through early July.

  • Depending on direction of travel, traffic is being detoured via US 12, US 63 and WIS 64 or US 12, WIS 79 and WIS 170.


Highway: US 12

Location: UP railroad bridge east of Hudson

Schedule: April 13 to late June

Cost: $1.24 million

Description of work: Replacing the concrete bridge deck, making concrete surface repairs at the abutments and girders, replacing the steel bearings at the east abutment, replacing the east abutment expansion joint, replacing the southwest wing wall top, replacing concrete pavement approach slabs and about 100 feet of roadway approaches and placing new pavement markings

Traffic Impacts: US 12 is closed at the bridge.

  • Traffic is being detoured via WIS 65 and I-94 and US 12.


Highway: I-94

Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson

Schedule: March 30 to mid-October, 2026 construction; and Sept. 9, 2024, to mid-October 2026, overall project

Cost: $20.08 million

Description of 2026 work: Removing and replacing the eastbound I-94 bridges; replacing I-94 pavement on both sides of structures in both directions; installing storm sewer; replacing guardrail and pavement markings; removing temporary structures and travel lanes; and restoring the median

Traffic Impacts: I-94 remains open to traffic, but:

  • Eastbound I-94 traffic is operating on temporary lanes built in the median in the 100th Street and Kinney Road work zones.

  • The speed limit in those work zones has been reduced to 60 mph.


Highway: I-94

Location: St. Croix River bridges between Hudson and Lakeland, Minn.

Schedule: April 6 to late October, 2026 construction; Sept. 29, 2025, to late October 2026, overall project

Cost: $9.85 million

Description of 2026 work: Construction on both bridges includes: Replacing the modular and expansion joints, placing a new polymer overlay on the bridge decks, making concrete surface repairs, cleaning of bridge bearings and replacing pavement markings. Construction on the westbound bridge also includes making repairs on the east and west abutment back walls, completing spot painting of bridge pin and hanger system. Construction on the eastbound bridge also includes repairing the east abutment back wall and replacing the sidewalk railing. Construction on the retaining wall on the Wisconsin approach: Replacing the block wall crossing under and adjacent to I-94 and parallel to the pedestrian path.

Traffic impacts: I-94 remains open to traffic, but motorists will encounter the following on:

  • Eastbound I-94:

    • Three lanes are open to traffic on the eastbound bridge; lanes are restricted to 11 feet in width.

  • Westbound I-94:

    • Two lanes are open to traffic, but one lane has been shifted onto the eastbound bridge.

      • The traffic split begins near the 11th Street overpass.

  • The Hudson to Lakeland/Afton Trail is anticipated to close to users Monday, June 22 just north of the westbound I-94 bridge on the Wisconsin side and just south of the eastbound bridge on the Minnesota side.

  • During closure of the trail, a shuttle service will make three roundtrips across the bridges daily, picking up passengers on the Wisconsin side first at 7 a.m., noon and 5 p.m. Sundays through Saturdays at the following.

§  Wisconsin side: Boat launch parking lot on WIS 35 across the street from the wastewater treatment plant, 505 3rd St., Hudson

§  Minnesota side: Southwest corner of Hudson Road North and Quinlan Avenue North in Lakeland



Sawyer County


Highway: County D

Location: Chippewa River Bridge east of Exeland in the town of Weirgor

Schedule: March 23 to late July

Cost: $1.08 million

Description of work: Replacing the bridge deck, making concrete surface repairs to the abutments, piers and girders, completing bridge joint, shoulder and guardrail work and replacing the roadway approach pavement

Traffic impacts: County D is closed at the Chippewa River.

  • Traffic is being detoured via WIS 40, WIS 70 and WIS 27.



Trempealeau County


Highway: Smikrud Road

Location: Grant Creek Bridge south of Ettrick in the town of Gale

Schedule: Feb. 19 to early July

Cost: $580,841

Description of work: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing the temporary bypass and structure

Traffic impacts: Motorists are using the new bridge, but motorists might encounter lane closures as finishing work is completed.


Highway: County D

Location: Elk Creek Bridge northeast of the unincorporated community of Elk Creek

Schedule: June 10 to mid-September

Cost: $826,726

Description of work: Replacing the bridge and roadway approaches and completing shouldering and guardrail work

Traffic impacts: County D is closed at the bridge.



Regionwide Pavement Marking Project


Highway: Various

Location: Barron, Bayfield, Buffalo, Burnett, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, St. Croix, Taylor, Trempealeau and Washburn

Schedule: April 14 to early August

Cost: $2.08 million

Description of work: Replacing pavement markings

Traffic impacts: Motorists will encounter daytime and nighttime lane closures depending on the location of work. For the coming week, crews are expected to work in the following counties on:

  • Bayfield County:

    • US 2, west of Iron River Bridge to US 63

  • Burnett and Polk counties:

    • WIS 35, Lanquist Street (Siren) to Polk Street (Frederic)

  • Douglas County:

    • US 53, south of Kent Road to US 2 East


For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region:


Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.

menomonie_minute-header_background.png

© 2026 MENOMONIE MINUTE. ALL RIGHTS RESERVED.

  • Facebook
bottom of page