Northwest Region Construction Update - July 17
- 4 days ago
- 21 min read

The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Ashland County
Highway: Prentice Avenue
Location: US 2 (Lake Shore Drive) to 6th Street East in Ashland
Schedule: May 4 to early July
Cost: $845,876
Description of work: Replacing the existing pavement structure, making subgrade improvements, modifying the vertical profile of the road to allow for better tie-ins, replacing substandard curb ramps, curb and gutter, adding two inlets just south of 3rd Street and replacing pavement markings and signage
Traffic impacts: Prentice Avenue is closed.
Highway: County GG
Location: McCarthy Creek Bridge southwest of Mellen
Schedule: May 26 to late July
Cost: $665,275
Description of work: Replacing the bridge, reconstructing the pavement on both sides of the bridge and replacing guardrail
Traffic impacts: County GG is closed from Conley Road to Clam Lake Road
Traffic is being detoured via WIS 13 and WIS 77.
Highway: WIS 77
Location: WIS 13 in Mellen to the Iron County line
Schedule: July 6 to early October
Cost: $3.59 million
Description of work: Milling off a portion of the existing pavement and placing new pavement; replacing storm sewer; installing centerline rumble strips; overlaying the deck on the Devil's Creek Bridge in Mellen; cleaning, removing or replacing culverts; replacing culvert end walls; replacing or removing guardrail; and placing new pavement markings
Traffic impacts: WIS 77 remains open to traffic, but motorists will encounter:
Single-lane closures controlled by flagging
Single-lane closures on the Devil’s Creek Bridge controlled by temporary traffic signals between Olson and Christ Lutz roads from Monday, July 20 to mid-August
Ashland and Sawyer counties
Highway: WIS 13 and WIS 77
Location: WIS 13, Price County line to Morse Road between Mellen and Glidden, and WIS 77, Teal River Bridge northeast of Hayward
Schedule: WIS 13, April 27 to late October; Work on WIS 77 expected to start in August
Cost: $5.19 million
Description of work: WIS 13, replacing, resetting, extending or abandoning more than 50 existing culvert pipes and constructing a new box culvert at Becky Creek; making concrete surface repairs at the bridge over Dryden Creek northwest of Glidden; patching the deck on the bridge over the Chippewa River southeast of Glidden; overlaying the deck with concrete on the bridge over Butternut Creek south of Butternut; and replacing guardrail at the structures and one other location in the project limits; WIS 77, milling and overlaying the existing bridge deck, overlaying concrete pavement approach slabs, milling and overlaying roadway approaches, making concrete surface repairs on parapets, grouting voids under abutments, supplementing riprap at abutments, adjusting guardrail and installing new pavement markings
Traffic impacts: WIS 13 remains open to traffic, but motorists will encounter:
Single-lane closures controlled by temporary traffic signals at Becky Creek and active culvert pipe installations
Signals at Becky Creek are in place continuously.
Those at culvert pipe locations are in place during work hours only.
Single-lane closures controlled by flagging during paving at culvert sites – typically on Fridays.
Barron County
Highway: County O
Location: East Branch Upper Pine Creek Bridge north of the village of Dallas
Schedule: June 15 to early August
Cost: $ $501,425
Description of work: Replacing the bridge and reconstructing 149.5 feet of approaching roadway
Traffic impacts: County O is closed at the structure, and traffic is being detoured via County D, WIS 25 and County U.
Highway: County O
Location: Wisconsin Avenue intersection in Rice Lake
Schedule: April 20 to late September
Cost: $1.1 million
Description of work: Realigning and extending the County O left-turn lanes, constructing right-turn lanes both north and south along Wisconsin Avenue, replacing traffic signals and adding sidewalk and a pedestrian crossing on County O
Traffic impacts: Motorists will encounter temporary lane closures during sidewalk construction on the southwest corner of the County O/Wisconsin Avenue intersection.
Highway: US 53 South
Location: Bridges between Cameron and New Auburn, structures over US 8, Knapp Street, County A, County AA and Carlson School Road, 2025; and structures over 20th Street, County I and the Chetek River, 2026
Schedule: Feb. 23 to October, 2026 construction; May 5, 2025, to October 2026, overall project
Cost: $10.91 million
Description of 2026 work: Replacing the decks on the bridges over the Chetek River and 20th Street; replacing the bridge over County I; milling pavement on both sides of each structure and placing new asphalt pavement on the approaches; milling and overlaying the pavement on the southbound US 53 on- and off-ramps at the County I interchange; and replacing guardrail, pavement markings and signage
Traffic impacts: Southbound US 53 remains open to traffic, but motorists will encounter:
Single-lane closures on southbound US 53 and a reduced speed limit of 60 mph.
Single-lane closures on County I through the duration of the project
Closure of the ramp from County I to southbound US 53
The ramp closure is anticipated to be in place through late September.
Traffic is being detoured on northbound US 53 to the US 8 interchange, where motorists will exit and then re-enter southbound US 53.
Highway: US 63
Location: Charrie Lane in Cumberland to the Washburn County line
Schedule: April 13 to late June
Cost: $4.64 million
Description of work: Removing a portion of the existing pavement and paving new asphalt, installing centerline and edge line rumble strips, cleaning or repairing culverts, reconstructing sidewalk curb ramps to Americans With Disabilities Act (ADA) compliance and placing new pavement markings
Traffic impacts: None; project complete.
Highway: US 63
Location: Beaver Dam Lake in Cumberland
Schedule: April 24 to early September
Cost: $2.64 million
Description of work: Removing the existing box culvert carrying Beaver Dam Lake under US 63, building a bridge with a longer span to replace the box culvert, removing the Lake Street Bridge, dredging Beaver Dam Lake under US 63 and the Lake Street Bridge, building an ATV trail on the east side of US 63 from Arcade Avenue to Nedvidek Street, reconstructing US 63 on both sides of the new bridge, reconstructing portions of Lake Street, Nedvidek Street and Babcock Avenue to match the raised profile of US 63 and constructing curb, gutter and sidewalk
Traffic impacts: US 63 is closed to traffic on both sides of the structure.
Traffic is being detoured via WIS 48, US 53 and WIS 70. In addition:
Lake Street is closed just past the boat landing.
Access to the boat landing is being maintained.
The Lake Street Bridge is open to emergency vehicles only through late July or early August.
Bayfield County
Highway: WIS 13
Location: Lake Superior Wayside between Iron River and Port Wing about 0.48 mile west of Airport Road
Schedule: July 13 to late November
Cost: $3.98 million
Description of work: On the shoreline from the west property line to Jardine Creek: Armoring the toe of the slope using a 6-inch-thick layer of bedding stone, a 3-foot-thick layer of underlying stone and a 6-foot-thick layer of armor stone; excavating a 4:1 slope from the newly constructed armored to the top of the existing slope; and stabilizing the excavated slope with turf reinforcement mat and garden with topsoil and seed. At the wayside: Milling 2 inches of existing asphalt and paving 2 inches of new asphalt in the parking lot and WIS 13 entrance; upgrading the walking path to meet Americans With Disabilities Act standards by grading base aggregate and overlaying with 2 inches of new asphalt; replacing the culvert and apron end walls below the walking path to the lake and at the WIS 13 entrance to the wayside; replacing the timber guard posts bordering the parking area; and repairing the crack in the concrete slab under the pavilion
Traffic impacts: WIS 13 remains open with minimal impacts to traffic, but the wayside is closed for the duration of work.
Highway: WIS 13
Location: Little Whittlesey Creek south of the city of Washburn
Schedule: June 8 to mid-October
Cost: $1.5 million
Description of work: Constructing a temporary bypass to carry WIS 13 traffic during construction, replacing the culvert pipes with a bridge, milling and paving about 1,000 feet of pavement approaching the bridge, restoring the stream bed, installing new guardrail, relocating the driveway of the US Fish and Wildlife Service facility, adding riprap and removing the temporary bypass
Traffic impacts: WIS 13 remains open to traffic, but motorists are using a temporary bypass to travel around the construction site.
Highway: US 2
Location: North Fish Creek Bridge southwest of the intersection of US 2 and WIS 13
Schedule: April 13 to mid-July
Cost: $1.69 million
Description of work: Replacing the bridge deck, repairing an abutment, resetting an inlet, completing minor paving on both sides of the bridge to adjust and smooth out roadway approaches and adjusting guardrail
Traffic impacts: US 2 is reduced to a single lane at the bridge.
The open lane has a maximum width of 13 feet.
Temporary traffic signals are controlling use of the single lane.
Motorists should expect delays.
The bridge is expected to fully open to traffic by mid-week the week of July 20.
The alternative oversize-overweight truck route follows US 53, WIS 77, WIS 13 and WIS 112.
Highway: US 63
Location: Long Lake branch in Drummond
Schedule: July 13 to late November, 2026 construction; project will shut down for winter, with work resuming in spring 2027
Cost: $4.59 million
Description of 2026 work: Drawing down Mill Pond, realigning the Long Lake branch and building a bypass to carry a single lane of traffic during 2027 construction
Traffic impacts: US 63 remains open to a single lane of traffic controlled by temporary traffic signals between Delta Drummond Road to Drummond Lake Road.
Buffalo County
Highway: County P
Location: Trempealeau River Bridge east of Fountain City in the town of Buffalo
Schedule: Feb. 23 to mid-October
Cost: $1.78 million
Description of work: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing temporary bypass and structure
Traffic impacts: County P remains open to traffic, but motorists are using a temporary road and bridge to bypass the work zone.
They might encounter flagging at the site for hauling in equipment and materials.
In addition, buoys have been added upstream and downstream to alert boating traffic of construction.
Highway: WIS 35 and WIS 54
Location: WIS 35, Indian Creek Road to old WIS 35; and WIS 54, Minnesota state line to WIS 35
Schedule: April 23 to early July
Cost: $6.41 million
Description of work: WIS 35, milling and overlaying the asphaltic pavement; repairing or replacing culverts to address deterioration; adjusting, repairing or replacing guardrail; improving drainage along WIS 35 just west of Lovers Lane; upgrading curb ramps to meet Americans With Disabilities Act standards; installing centerline and shoulder rumble strips; and adding new pavement markings; WIS 54, milling and overlaying the asphaltic pavement, replacing weigh-in-motion sensors in the roadway; installing centerline and shoulder rumble strips; and adding new pavement markings
Traffic Impacts: None; current work operations are suspended until mid-August.
Highway: US 10
Location: Pepin County line to County A in Mondovi
Schedule: June 30 to late August
Cost: $3.35 million
Description of work: Milling the pavement surface and overlaying the roadway with asphalt, installing centerline rumble strips; replacing guardrail and flattening slopes at guardrail end terminals; cleaning, repairing or replacing culvert pipes; cleaning ditches to remove sediment buildup; and installing new pavement markings
Traffic impacts: US 10 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging.
Burnett County
Highway: WIS 35
Location: Lanquist Street in Siren to WIS 70 East
Schedule: May 4 to mid-October
Cost: $8.55 million
Description of work: Replacing pavement with new concrete from Lanquist Street to Southshore Drive, replacing storm sewer and expanding its capacity from Lanquist to Works Progress Street, resurfacing the roadway from Southshore Drive to WIS 70 East, reviewing and revising access points, improving turning movements in all quadrants at the WIS 35 and WIS 70/County B intersection in the city of Siren, replacing traffic signals, replacing curb ramps and removing extra lanes from Park Street to Northshore Drive to reduce flooding potential
Traffic impacts: WIS 35 remains open to traffic, but motorists will encounter:
Shoulder closures on northbound WIS 35 from Lanquist Street to Bradley Street; southbound WIS 35 from the WIS 35/70 intersection to Bacon Street; and east- and westbound WIS 70 from 1st Avenue to the WIS 35/70 intersection
Various shoulder closures on north- and southbound US 53 from Southshore Drive to WIS 35/70 roundabout
Closure of WIS 35 to northbound traffic from Lanquist Street to Southshore Drive
WIS 35 is open to southbound traffic only in that segment.
Northbound car detour: County B, 4th Avenue North and Elizabeth Street
Truck detour: WIS 70/MN 70, I-35 (MN), MN 48/WIS 77 and WIS 35
Chippewa County
Highway: WIS 124
Location: Duncan Creek Bridge to County S
Schedule: April 13 to mid-June
Cost: $2.68 million
Description of work: Milling off a portion of the pavement and placing new asphalt pavement, resurfacing the County S roundabout and replacing the central island truck apron pavement, replacing culverts, cleaning ditches, upgrading sidewalk curb ramps and replacing pavement markings
Traffic Impacts: None currently, but the roundabout at WIS 124/County S is scheduled to close to traffic on Monday, July 20.
The closure is anticipated to be in place for 17 working days.
Traffic will be detoured via Business 29 (West River Street), US 53 and County B.
Chippewa and Clark counties
Highway: WIS 29
Location: 320th Street east of Boyd to Koser Avenue west of Thorp
Schedule: May 11 to mid-September
Cost: $9.35 million
Description of work: Patching the concrete pavement, placing 3.75 inches of asphalt over the existing roadway, removing a portion of the existing pavement on the WIS 29 on- and off-ramps at the County H interchange in Stanley and on County H between the east- and westbound ramps and placing new asphalt pavement, repairing culverts as needed, rehabilitating the structure over Hay Creek east of Boyd and closing and removing the intersection on WIS 29 at 320th Street per the town of Delmar’s request
Traffic impacts: None; WIS 29 is fully open to traffic through 6 a.m. Monday, July 20. At that time, crews will close lanes in both directions for the length of the work zone.
Clark County
Highway: WIS 29
Location: County D in Owen to WIS 13 in Abbotsford
Schedule: March 30 to early October
Cost: $17.37 million
Description of work: Repairing the existing concrete pavement on WIS 29 and the ramps at the County E interchange and then overlaying the roadway and ramps with asphalt pavement; overlaying the ramps at Cardinal Avenue east of Owen and Hi Line Avenue in Abbotsford with asphalt; replacing guardrail to meet current WisDOT standards; repairing the decks on the east- and westbound WIS 29 bridges over County D and the railroad tracks to the east and placing a thin bonded polymer overlay over them; cleaning and repairing culverts to improve drainage; repairing the median inlets near Owen adjacent to concrete barrier wall; and completing minor grading of ditches
Traffic Impacts: WIS 29 remains open to traffic, but motorists will encounter:
Outside lane closures in both directions from County D to County E and the Dill Creek Bridge east of Curtiss to WIS 13
Closure of eastbound WIS 29 on- and off-ramps at the County E interchange in the Curtiss area
The ramp closures are expected to be in place for two weeks.
Highway: WIS 98
Location: WIS 73 south of Greenwood to Helm Street in Loyal
Schedule: July 2 through mid-September
Cost: $1.8 million
Description of work: Replacing the existing concrete pavement in select areas of pavement failure due to poor soils; replacing base material and adding geo-grid in those poor soils areas; making concrete joint repairs in other areas; replacing, repairing, resetting, extending or cleaning culvert pipes; and replacing pavement markings
Traffic Impacts: WIS 98 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging operations and temporary traffic signals.
Douglas County
Highway: County B
Location: Lake Nebagamon Creek Bridge east of US 53
Schedule: May 18 to mid-July
Cost: $565,907
Description of work: Replacing the bridge, reconstructing pavement on both sides of the bridge and grading
Traffic Impacts: None; project complete.
Highway: WIS 13
Location: Bridge over US 2/53 southeast of Superior
Schedule: June 8 to late July
Cost: $1.43 million
Description of work: Replacing bridge joints, making surface repairs to abutments, cleaning and painting bridge girders and bearings, replacing concrete approach slabs at each end of bridge, replacing asphalt roadway approaches for about 100 feet and replacing the guardrail bridge connections
Traffic Impacts: WIS 13 and US 2/53 remain open to traffic, but motorists will encounter:
Single-lane closures on WIS 13 controlled by temporary traffic signals
Single-lane and shoulder closures on US 2/53 once shoulder strengthening and bridge girder painting work begin
Highway: WIS 105
Location: Unnamed tributary of the Pokegama River in Superior
Schedule: June 15 to late October
Cost: $3.06 million
Description of work: Removing the existing culvert, building a temporary bypass to carry a single lane of traffic during construction, constructing a bridge to replace the culvert, replacing pavement approaching the new structure, installing guardrail, removing the temporary bypass and repairing slopes disturbed by construction
Traffic Impacts: WIS 105 remains open to traffic, but motorists are using a bypass road controlled by temporary traffic signals to get around the construction site.
Truck traffic is being detoured.
Truck traffic heading west is being detoured north to US 2 and MN 23 at 61st Street and Tower Avenue.
Truck traffic heading east is being detoured north to MN 23 and US 2 at MN 23 and East McCuen Street in Duluth, Minn.
Dunn County
Highway: County D
Location: Red Cedar River Bridge
Schedule: July 6 to mid-August
Cost: $816,921
Description of work: Overlaying the bridge deck with concrete and repairing pier scour
Traffic Impacts: County D is closed at the structure.
Highway: County P
Location: Irving Creek west of Menomonie
Schedule: May 18 to early July
Cost: $547,773
Description of work: Replacing the structure with a twin-cell box culvert and reconstructing pavement on both sides of the new structure
Traffic Impacts: None; project complete.
Highway: County Q
Location: North Branch Wilson Creek Bridge northwest of Knapp
Schedule: June 8 to late July
Cost: $430,297
Description of work: Replacing the bridge and reconstructing pavement on both sides of the new structure
Traffic Impacts: County Q is closed at the structure.
Highway: WIS 25
Location: I-94 in Menomonie to County D
Schedule: April 16 to early August
Cost: $4.98 million
Description of work: Removing a portion of the existing pavement from the bridge over I-94 to the railroad bridge and placing new asphalt pavement; recycling a portion of the existing pavement, mixing it with a stabilizing agent, relaying it and placing new asphalt over the roadway from the railroad bridge to County D; adjusting or replacing guardrail; and upgrading pedestrian curb ramps and traffic signals
Traffic Impacts: WIS 25 is open to traffic, but motorists will encounter single-lane closures controlled by flagging.
Highway: WIS 85
Location: Just west of the north junction of County O west of Rock Falls to approximately 2,100 feet west of 1010th Street northeast of Caryville
Schedule: April 27 to mid-August
Cost: $3.94 million
Description of work: Removing a portion of the existing pavement from just west of the north junction of County O to the south junction of County H and placing new pavement, removing and recycling a portion of the existing pavement from the south junction of County H to approximately 2,100 feet west of 1010th Street and overlaying the roadway with new pavement, widening the paved shoulders from 3 to 5 feet, installing centerline and shoulder rumble strips from the south junction of County H to about 2,100 feet west of 1010th Street, replacing the existing drainage structure under WIS 85 east of the north junction of County H with a dual box culvert, replacing a cattle pass that is no longer used with a culvert pipe, removing guardrail and improving the Chippewa River State Trail crossing to meet Americans With Disabilities Act standards
Traffic Impacts: WIS 85 is open to traffic, but motorists will encounter lane closures controlled by flagging operations.
Highway: US 12 and WIS 40
Location: US 12, Princeton Drive in Elk Mound to just north of WIS 29; and WIS 40, US 12 to County M in the village of Colfax
Schedule: March 30 to October
Cost: $8.99 million
Description of work: Milling 2.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in rural areas; milling 3.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in urban areas; replacing joints on the Eighteen Mile Creek Bridge in village of Colfax; placing centerline rumble strips in rural areas; replacing cross culverts, guardrail and sidewalk curb ramps; and replacing the railroad crossing in the village of Colfax
Traffic Impacts: Motorists will encounter single-lane closures controlled by flagging operations from Elk Mound through Colfax.
The bridge carrying US 12 over WIS 29 northwest of Elk Mound reopened to traffic this morning.
WIS 40 is anticipated to be fully closed south of 855th Street from Monday to Friday, July 20-24.
o  The closure is located about halfway between N8335 WIS 40 and 855th Street.
o  Traffic will be detoured via WIS 29, I-94, WIS 25 and WIS 170.
Eau Claire County
Highway: WIS 93, WIS 312 and US 12
Location: WIS 93, East Hamilton Avenue, Eau Claire, to Deerfield Road, town of Washington; WIS 312, Old Wells Road to US 53, all in Eau Claire; and US 12: Truax Boulevard, Eau Claire, to Mayer Road, Altoona
Schedule: March 30 to mid-September
Cost: $2.91 million
Description of work: Reconstructing noncompliant curb ramps and upgrading pedestrian crossings that aren’t consistent or not fully provided where needed
Traffic Impacts: Motorists might encounter short-term nighttime lane closures on US 12 and WIS 93 as pavement marking work is completed.
Highway: I-94
Location: US 53 interchange to Mallard Road southwest of Eau Claire
Schedule: March 23 to late November, 2026 construction; and March 4, 2024, to late November 2026, overall project
Cost: $69.9 million
Description of 2026 work: Replacing the pavement on eastbound I-94 from Otter Creek to Mallard Road, the eastbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under eastbound I-94 near County D; completing shoulders, removing temporary lanes and structures and restoring the interstate’s median
Traffic Impacts: Motorists will encounter lane closures in both directions during off-peak travel times and a reduced speed limit of 60 mph in the work zone.
County D is closed at I-94.
Traffic is being detoured via US 53, County J, County IJ and County JJ.
Jackson County
Highway: Cain Road
Location: North Branch Trempealeau River Bridge north of Hixton
Schedule: June 29 through early October
Cost: $665,514
Description of work: Building a new bridge north of the existing alignment, reconstructing approximately 1,020 feet of roadway approaches, excavating a marsh, grubbing, placing riprap and removing the existing structure
Traffic Impacts: The north shoulder is closed.
Pepin County
Highway: Dorwins Mill Road
Location: Bear Creek Bridge east of Durand
Schedule: May 18 to late July
Cost: $679,659
Description of work: Replacing the bridge and reconstructing roadway on both sides of the structure
Traffic Impacts: Dorwins Mill Road is closed at the bridge.
Highway: US 10
Location: WIS 25 North intersection west of Durand
Schedule: July 7 to early November
Cost: $2.62 million
Description of work: Constructing a single-lane roundabout at the intersection, installing curb and gutter, replacing culverts and storm sewer and installing lighting
Traffic Impacts: US 10 and WIS 25 North will remain open to traffic during construction, but motorists will encounter:
Shoulder closures throughout the duration of the project
Switches to temporary lanes throughout the staging of reconstruction of the intersection
Intermittent flagging operations during each stage
Polk County
Highway: WIS 46
Location: US 8 to WIS 35
Schedule: April 15 to early October
Cost: $8.49 million
Description of work: Recycling 4 inches of pavement in place on the rural portion of the project; placing 2.75 inches of new asphalt and installing centerline rumble strips; milling 3.25 inches of pavement in the village of Balsam Lake and placing 3.35 inches of new asphalt; cleaning, extending, lining or replacing culverts; replacing or adjusting existing guardrail; and replacing curb ramps in the village of Balsam Lake
Traffic impacts: Motorists will encounter moving single-lane closures controlled by flagging on open segments of WIS 46.
WIS 46 is closed from 140th Avenue to 150th Avenue but is expected to reopen to traffic the week of July 20.
Highway: US 8
Location: WIS 35 North to WIS 46 South
Schedule: May 11 to late August
Cost: $7.52 million
Description of work: Milling 2.25 inches of existing asphaltic surface and placing 3.25 inches new asphalt; reconstructing two locations of roadway where sloughing is occurring; widening the paved shoulders from 3 to 5 feet; installing centerline and shoulder rumble strips; cleaning, extending, lining or replacing existing culverts and replacing deteriorating end walls on some structures; replacing or adjusting guardrail; and completing roadside maintenance, including clearing and ditchingTraffic impacts: US 8 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging at various locations in the project limits.
Motorists should expect delays.
Rusk County
Highway: US 8
Location: Little Soft Maple Creek northwest of Weyerhaeuser
Schedule: June 23 to late September
Cost: $1.92 million
Description of work: Constructing a temporary bypass on the north side of US 8 to carry traffic during construction, removing the existing box culvert, constructing a single-span bridge half at a time to replace it, replacing roadway approach pavement on both sides of the structure and installing guardrail
Traffic impacts: US 8 remains open to a single lane of traffic controlled by temporary traffic signals.
St. Croix County
Highway: WIS 35/64 and WIS 64
Location: WIS 35/64, 150th Avenue northeast of Houlton to County C; and WIS 64, WIS 35 to 142nd Street in New Richmond
Schedule: April 13 to September
Cost: $9.96 million
Description of work: Performing spot repairs on the driving lanes in both directions where deterioration exists, overlaying existing concrete with asphalt at select locations in both directions of travel, installing new pavement markings and shoulder rumble strips, resurfacing the existing shoulders, replacing guardrail at structures and signage and cleaning or riprapping culvert end walls
Traffic Impacts: WIS 35/64 and WIS 64 remain open to traffic, but motorists will encounter:
Single-lane closures in both directions
Highway: WIS 128
Location: US 12 to WIS 170 in Glenwood City
Schedule: May 26 to late August
Cost: $6.08 million
Description of work: Recycling 3.75 inches of the existing asphaltic surface and paving 2.75 inches over the recycled pavement in the rural section of the project; milling approximately 3.25 inches of the existing asphaltic surface and paving the roadway with 3.25 inches of hot-mix asphalt in the urban section; placing centerline rumble strips; overlaying the deck on the bridge over Tiffany Creek in Glenwood City; updating guardrail throughout the project corridor; cleaning or replacing culvert pipes; updating sidewalk curb ramps in Glenwood City; and installing new pavement markings
Traffic Impacts: WIS 128 is open to traffic, but motorists will encounter lane closures controlled by flagging.
Highway: I-94
Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson
Schedule: March 30 to mid-October, 2026 construction; and Sept. 9, 2024, to mid-October 2026, overall project
Cost: $20.08 million
Description of 2026 work: Removing and replacing the eastbound I-94 bridges; replacing I-94 pavement on both sides of structures in both directions; installing storm sewer; replacing guardrail and pavement markings; removing temporary structures and travel lanes; and restoring the median
Traffic Impacts: I-94 remains open to traffic, but:
Eastbound I-94 traffic is operating on temporary lanes built in the median in the 100th Street and Kinney Road work zones.
The speed limit in those work zones has been reduced to 60 mph.
Highway: I-94
Location: St. Croix River bridges between Hudson and Lakeland, Minn.
Schedule: April 6 to late October, 2026 construction; Sept. 29, 2025, to late October 2026, overall project
Cost: $9.85 million
Description of 2026 work: Construction on both bridges includes: Replacing the modular and expansion joints, placing a new polymer overlay on the bridge decks, making concrete surface repairs, cleaning of bridge bearings and replacing pavement markings. Construction on the westbound bridge also includes making repairs on the east and west abutment back walls, completing spot painting of bridge pin and hanger system. Construction on the eastbound bridge also includes repairing the east abutment back wall and replacing the sidewalk railing. Construction on the retaining wall on the Wisconsin approach: Replacing the block wall crossing under and adjacent to I-94 and parallel to the pedestrian path.
Traffic impacts: I-94 remains open to traffic, but motorists will encounter the following on:
Eastbound I-94:
Three lanes are open to traffic on the eastbound bridge; lanes are restricted to 11 feet in width.
Westbound I-94:
Two lanes are open to traffic, but one lane has been shifted onto the eastbound bridge.
The traffic split begins near the 11th Street overpass.
o  Westbound I-94 will be reduced to a single lane east of the Carmichael Road interchange (exit 2) from 9 p.m. to 5 a.m. for four nights beginning Monday, July 20 to complete concrete patching between the Carmichael interchange and the St. Croix River Bridge.
The pavement repair work also will result in the closure of the ramp to WIS 35 North (exit 1) from 9 p.m. Thursday to 5 a.m. Friday.Â
The Hudson to Lakeland/Afton Trail is closed just north of the westbound I-94 bridge on the Wisconsin side and just south of the eastbound bridge on the Minnesota side.
o  During closure of the trail, a shuttle service is making three roundtrips across the bridges daily, picking up passengers on the Wisconsin side first at 7 a.m., noon and 5 p.m. Sundays through Saturdays at the following.
§ Wisconsin side: Boat launch parking lot on WIS 35 across the street from the wastewater treatment plant, 505 3rd St., Hudson
§ Minnesota side: Southwest corner of Hudson Road North and Quinlan Avenue North in Lakeland
Sawyer County
Highway: County D
Location: Chippewa River Bridge east of Exeland in the town of Weirgor
Schedule: March 23 to late July
Cost: $1.08 million
Description of work: Replacing the bridge deck, making concrete surface repairs to the abutments, piers and girders, completing bridge joint, shoulder and guardrail work and replacing the roadway approach pavement
Traffic impacts: County D is closed at the Chippewa River.
Traffic is being detoured via WIS 40, WIS 70 and WIS 27.
Sawyer and Price counties
Highway: WIS 70
Location: County GG in the unincorporated community of Loretta in Sawyer County to Pixley Wilderness West Road in the Price County town of Lake west of Fifield
Schedule: June 15 to early August
Cost: $5.5 million
Description of work: Removing a portion of the existing asphalt, repaving the roadway with new asphalt pavement, installing centerline rumble strips, replacing or repairing guardrail as needed, placing gravel along the shoulders and replacing pavement markings
Traffic impacts: WIS 70 remains open to traffic, but motorists will encounter lane closures controlled by flagging.
Trempealeau County
Highway: County D
Location: Elk Creek Bridge northeast of the unincorporated community of Elk Creek
Schedule: June 10 to mid-September
Cost: $826,726
Description of work: Replacing the bridge and roadway approaches and completing shouldering and guardrail work
Traffic impacts: County D is closed at the bridge.
Highway: County D
Location: Osley Lane south of Ettrick to the Jackson County line
Schedule: July 13 to mid-October
Cost: $3.21 million
Description of work: Pulverizing and relaying the existing pavement and underlying base aggregate, paving 4 inches of new asphalt pavement; improving drainage by completing curb and gutter, ditching and storm sewer work; replacing culvert pipes; replacing or extending box culverts; replacing guardrail terminal ends; and placing new pavement markings
Traffic impacts: County D is closed to through traffic.
Regionwide Pavement Marking Project
Highway: Various
Location: Barron, Bayfield, Buffalo, Burnett, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, St. Croix, Taylor, Trempealeau and Washburn
Schedule: April 14 to early August
Cost: $2.08 million
Description of work: Replacing pavement markings
Traffic impacts: Motorists will encounter daytime and nighttime lane closures depending on the location of work. Once work resumes Monday, July 6, crews plan to work in the following counties:
Douglas County:
US 53, south of Kent Road/County E to US 2 East
Dunn County:
I-94 ramp and southbound WIS 25
St. Croix County:
WIS 35, Front Street to North End Road
WIS 35, WIS 65 North to I-94
Washburn County:
US 53 at mile marker 153
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region:
Follow us on X: @WisDOTnorthwest
Visit the region’s 511 website: projects.511wi.gov/region/northwest/
Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.