US12/WIS 29 and other area summer road construction projects


US 12/WIS 29, 6th Street - 21st Street, Menomonie

Construction is to begin late June or early July and completion is expected in September.


This project includes:

  • Milling the existing concrete road surface and overlaying it with asphalt.

  • Reducing the through lanes in each direction from two to one and adding a shared left-turn lane in the center of the road between both through lanes.

  • Using the remaining width of the road between the through lane and outside curb for bike traffic and right-turning vehicles needing to decelerate outside of the through lane.

  • Closing the 5th Avenue East intersection with US 12/WIS 29 to allow for the development of the two-way, left-turn lane at the west end of the project.

  • Improving curb ramps where necessary.

During construction, no full closure of US 12/WIS 29 is expected. Most of the work will be completed under traffic using short-term lane closures with flagging operations and temporary side road closures. Lane closures will be avoided during peak morning and afternoon traffic times.


More information about this project can be found here.


Highway 25

Road construction recently began on Highway 25 south of Menomonie from 490th Street to the Red Cedar River. This project will include resurfacing Highway 25, replacing an aging culvert and curb and gutter at spot locations, adding a dedicated turn lane at 380th Avenue, installing centerline rumble strips, widening paved shoulders and clearing ditches.


This project is expected to be completed in August. During construction, motorists will encounter daytime single-lane closures controlled by flagging operations.


Wilson Creek Bridge

According to the Wisconsin DOT website, the updates on Crescent Street and Stout Road in the City of Menomonie are scheduled to take place in 2022.be completed in August. US 12 will remain open to traffic. Motorists will use a one-lane bypass controlled by temporary traffic signa


Dunn County Projects

Dunn County has a number of projects scheduled for this summer for county roads. Improvements are scheduled for County Highway Q, County Highways Q and W, County Highway V and County Highway Z. Follow this link for specific information on these projects.


All information taken from the Wisconsin Department of Transportation website.